| # | Prioridad | No. parte | Guía | Inv. inicio | Inv. STD | GAP vs STD | Demanda | Producir (pzs) | Cajas | Horas | Horas acum. | No cabe | Inv. final | Días de cobertura | S48 | S49 | S50 | S51 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 510-60172-3W0-A000-H1 | WIP × | -768 | 6,300 | -7,068 | 4,320 | 11,400 | 380 | 56.7 | 56.7 | 6,312 | 7.0 | · | 11,400 | 3,780 | 4,500 | |
| 2 | 2 | 500-60174-3W0-A000-H1 | WIP × | 3,197 | 6,300 | -3,103 | 4,320 | 7,440 | 248 | 37.0 | 93.6 | 6,317 | 7.0 | 1,410 | 7,440 | 2,220 | 6,060 | |
| 3 | 6 | 510-60122-3W0-A000-H1 | WIP | 8,106 | 8,100 | 6 | 4,860 | 1,680 | 56 | 8.3 | 102.0 | 3,180 | 4,926 | 5.5 | 8,730 | 1,680 | 6,420 | 5,040 |
| Aquí se acaba la capacidad de la semana (102.1 h) — lo de abajo no cabe completo | ||||||||||||||||||
| 4 | 6 | 500-60124-3W0-A000-H1 | WIP | 8,113 | 8,100 | 13 | 4,860 | 0 | 0 | 102.0 | 4,860 | 3,253 | 3.6 | 6,270 | · | 8,100 | 4,920 | |